HomePlanning law
We use cookies to measure our website's audience. You may object at any time to processing based on legitimate interest by clicking 'Decline'. For more information: Privacy policy
Public law

Planning and Building Permit Lawyer in Grenoble and the Alps: Isère (38), Savoie (73), Haute-Savoie (74)

Grenoble, l'Isère et le massif de Belledonne
Contents
Our specialists
Laurent Bidault
Nicolas Machet

Alpine planning law follows rules found nowhere else. And for good reason!

The loi Montagne (French Mountain Act) governs development in municipalities that host ski resorts. New tourist developments (unités touristiques nouvelles) subject leisure property projects to a procedure of their own. Natural risk prevention plans deal with avalanches, torrential floods, rockfalls and landslides. And in narrow valleys, the scarcity of buildable land sharpens every neighbour dispute.

On top of this, until 2030, the Olympic timetable even changes the rules on which court has jurisdiction.

Whether you are a developer, a ski lift operator, a hotelier, a manufacturer in the Grésivaudan valley or a property owner in a resort, a refusal of a building permit or a third-party challenge can cost you a season. Maître Laurent Bidault brings his expertise in planning law to Alpine projects.

Laurent Bidault, your planning law expert in Grenoble

Working in the Alps requires a thorough command of the Grenoble-Alpes Métropole intermunicipal local plan (PLUi) and the planning documents of mountain municipalities, available on the Géoportail de l'urbanisme, as well as the natural risk prevention plans listed on Géorisques.

The firm defends your permits before the tribunal administratif de Grenoble (Grenoble Administrative Court), then before the cour administrative d'appel de Lyon (Lyon Administrative Court of Appeal), whose jurisdiction covers the courts of Clermont-Ferrand, Dijon, Grenoble and Lyon (article R. 221-7 of the code de justice administrative).

A jurisdiction rule that few operators are yet aware of, and which changes everything until 2030.

In view of the 2030 Winter Olympic and Paralympic Games, article R. 311-4 of the code de justice administrative gives the cour administrative d'appel de Marseille (Marseille Administrative Court of Appeal) jurisdiction at first and last instance over all disputes concerning planning, development, land acquisition, infrastructure, facilities, roads and even alpine or Nordic ski runs, where they are even partly linked to the organisation of the Games, as well as the planning documents on which they depend. This jurisdiction applies until 10 March 2030.

The consequence is practical and immediate: for these projects, neither the Grenoble Administrative Court nor the Lyon Court of Appeal has jurisdiction, and there is no appeal. An application lodged with the usual court will be dismissed or transferred, with the delays that entails. Before bringing any proceedings, we systematically check whether the project falls within this scope.

For projects outside this scope, article R. 811-1-1 of the same code may also remove the right of appeal, until 31 December 2027, for challenges to permits for buildings with more than two dwellings in the municipalities listed under article 232 of the code général des impôts (French General Tax Code), which includes several Alpine municipalities.

In practice, four situations where the project is decided

Challenging a refusal of a building permit

Loi Montagne, exposure to a natural hazard, integration into the site, insufficient network capacity at peak tourist periods: we review the lawfulness of the refusal and bring the court challenge.

Defending your permit against a third-party challenge

  1. Admissibility: the applicant's standing to bring proceedings and notification of the challenge. Challenges by associations are common in mountain areas: their statutory purpose and how long it has existed deserve careful scrutiny.
  2. Defence on the merits: rebutting the grounds raised and dealing with the presumption of urgency in suspension proceedings (référé-suspension), a decisive point when the works must be completed before the season opens.
  3. Counter-attack: damages for abusive proceedings, article L. 600-7 of the code de l'urbanisme (French Planning Code).

Securing the project upstream: the risk audit

In the mountains, a preliminary audit is decisive, because constraints accumulate: loi Montagne, UTN procedure, risk prevention plan, network capacity. An operational planning certificate makes it possible to freeze the applicable rules before committing to the design of a project whose construction window is, by nature, short.

Regularisation and lapse

Non-compliant works, a recorded breach, the threat of demolition: defence and regularisation. A sensitive point at altitude, where building sites shut down in winter: a permit lapses not only when its period of validity expires, but also if works are interrupted for more than a year (article R. 424-17 of the code de l'urbanisme). The chronology of interruptions must be documented.

Operational expertise for mountain projects

Loi Montagne and new tourist developments

This is the core of Alpine planning law. The loi Montagne restricts development that is not continuous with existing settlements and protects pastoral land, forests and lake shores. Leisure property, ski lift and ski area development projects are also subject to the new tourist development (UTN) regime, incorporated into planning documents since the 2016 reform: a UTN that is poorly aligned with the SCOT (territorial coherence scheme) or the PLU (local plan) undermines the whole project. We review this chain of documents and act to challenge the planning document itself when it is the source of the blockage.

Natural risks: avalanches, torrential floods, rockfalls

Alpine natural risk prevention plans impose some of the heaviest requirements in France, up to a ban on building. They are drawn up on the basis of hazard studies whose methodology and currency can be challenged, and their application to a given plot is not always accurate.

2030 Winter Olympic Games

Projects linked to the Games are subject to the special litigation regime described above, but also to accelerated development procedures. We assist the operators concerned, whether in defending a permit or challenging a decision, taking into account the absence of any appeal.

Industry, research and hydroelectricity

The Grésivaudan valley and the Grenoble area are a hub for microelectronics and research. We defend permits for site extensions, which are often subject to the rules on classified installations (ICPE), and act on energy projects: solar power plants, anaerobic digestion units and network equipment. See our page on energy and infrastructure law.

Acting in Grenoble, Isère and the two Savoie departments

Maître Laurent Bidault acts throughout Isère (38), in Grenoble, Vienne, Bourgoin-Jallieu and the Oisans, Savoie (73), in Chambéry, Albertville and the Tarentaise, and Haute-Savoie (74), in Annecy, Chamonix and Thonon-les-Bains, as well as in the Drôme and the Hautes-Alpes. For projects in the Lyon area, see our page building permit lawyer in Lyon.

Ils ont fait appel à NOVLAW avocats

Chargement…

Frequently asked questions on

Planning law

What is the time limit for lodging an appeal on points of law against a judgment of an Administrative Court of Appeal?

The time limit for lodging an appeal on points of law (pourvoi en cassation) against a judgment of an Administrative Court of Appeal is two months from notification of the court's decision. However, this time limit is reduced to 15 days where the case concerns summary proceedings (référé).

How can a building permit be challenged?

A building permit is challenged before the administrative court, by means of an application for judicial review (recours pour excès de pouvoir), within two months from the first day of a continuous two-month period during which the notice has been properly displayed on the site. If the notice was displayed irregularly or not at all, a challenge remains possible for six months from completion of the works. Two admissibility conditions must be met: the applicant must demonstrate standing, i.e. a direct impact on the conditions of occupation, use or enjoyment of their property; and the challenge must be notified to the author of the decision and to its beneficiary within fifteen days of being filed, by registered letter with acknowledgement of receipt. An informal appeal (recours gracieux) to the mayor remains possible, within one month, but it no longer extends the time limit for bringing proceedings for decisions taken on or after 28 November 2025 (Article L. 600-12-2 of the French Planning Code, introduced by the law on simplifying planning law of 26 November 2025). You should therefore not wait for the town hall's response before applying to the court. An application for suspension (référé-suspension) may be brought alongside the action on the merits to have the works halted.

What remedies are available against a building permit or prior declaration?

Third parties with standing, such as neighbours or associations, have two months from the first day of a continuous period of proper display of the notice on the site to apply to the administrative court. Two procedural rules determine admissibility: the challenge must be notified to the author of the decision and to its beneficiary within fifteen days of being filed, and standing must be established in detail. A decisive strategic point: since the law on simplifying planning law of 26 November 2025, an informal appeal (recours gracieux) no longer extends the time limit for bringing proceedings before the court for decisions taken on or after 28 November 2025. Waiting for the town hall's response therefore exposes you to the risk of being time-barred. Alongside the action on the merits, an application for suspension (référé-suspension) can be made to have the works halted.

What remedies are available against a refusal of a building permit?

Any refusal must state its legal and factual grounds. The first step is to analyse those grounds to determine whether they can be challenged in law or whether they reveal an obstacle that could be removed by amending the project. An application for judicial review (recours pour excès de pouvoir) must be lodged with the administrative court within two months of notification of the refusal. If the refusal is annulled, the court may order the administration to re-examine the application and, where the project complies with planning rules, to grant the authorisation. A point to watch: since the law on simplifying planning law of 26 November 2025, an informal appeal (recours gracieux), which must now be lodged within one month, no longer extends the time limit for bringing proceedings before the court. For decisions taken on or after 28 November 2025, you must apply directly to the court, or lodge both appeals at the same time.

What is the time limit for appealing a decision of an administrative court?

The time limit for appealing a decision of an administrative court (tribunal administratif) is two months from notification of the judgment. This time limit is only 15 days if the decision is an interim relief order (référé).

What is the right of retrocession?

If the local authority wishes to change the purpose or use of the property within 5 years of its acquisition, it must inform the former owner and offer them priority to acquire it. If the former owner declines, the local authority must inform the ousted prospective buyer named in the declaration of intention to sell (déclaration d'intention d'aliéner), and offer them priority to acquire the property.

What is the right to compel purchase (droit de délaissement)?

The right to compel purchase (droit de délaissement) is the right given to the owner of a property subject to a public utility easement (a reserved site in the local urban plan or PLU, an expropriation zone) to require the public authority to purchase the property. This right enables the owner to escape a deadlock caused by the public constraint weighing on their property. The authority then has one year in which to decide on the acquisition.

What is a carte communale?

The carte communale (municipal land-use map) is the equivalent of the PLU (local urban plan) for small municipalities that have chosen not to adopt one. It defines the areas where building is permitted, as well as the public utility easements affecting land use.

What is the commercial pre-emption right?

The commercial pre-emption right is a tool available to municipalities to combat the decline of town centres and ensure that local shops are maintained. The purpose of this pre-emption right is therefore to maintain or reintroduce diversity in local economic activity.

What is a prior declaration of works?

The prior declaration of works (déclaration préalable de travaux) is a planning authorisation that must be obtained before smaller-scale works begin. It is less demanding than a building permit and covers less significant construction and works. This declaration is mandatory and largely shares the procedural requirements of the building permit.

What is a building permit?

A building permit is a planning authorisation that must, in most cases, be obtained before works begin, whether to build, demolish or alter a structure, regardless of the type of owner or structure. It generally concerns new constructions and major alterations to existing buildings.

What is a SCOT?

The SCOT (Schéma de cohérence territoriale, territorial coherence scheme) is a long-term strategic inter-municipal planning document covering an urban area or a large living or employment area. It incorporates all higher-level planning documents; PLUs, PLUis and cartes communales therefore refer directly to the SCOT.

Can the municipality exercise its right of pre-emption?

Yes. If your property is located in a pre-emption zone (DPU), the municipality can take the place of the buyer when the Declaration of Intention to Sell (Déclaration d'Intention d'Aliéner, DIA) is signed. However, this decision must be strictly justified by a genuine development project in the general interest. We can assist you in challenging the lawfulness of the pre-emption or in negotiating the sale price before the expropriation judge.

Is a building permit required for a relay antenna?

A relay antenna requires a prior declaration where its footprint and floor area exceed 5 m² but do not exceed 20 m². A building permit is required if the antenna's footprint or floor area exceeds 20 m², or if the antenna is located within the boundaries of remarkable heritage sites (sites patrimoniaux remarquables) or in the vicinity of historic monuments and listed sites.

How can you ensure that a project complies with the PLU?

Before submitting an application, our firm carries out a thorough audit of your project against the rules of the Local Urban Plan (PLU) (zoning, height, footprint, parking). We can also apply for a planning certificate (certificat d'urbanisme, either detailed or informational) to freeze the rules applicable to your land.

What are the requirements for displaying a building permit?

Display on the site is mandatory whatever the operation, and whether the permit was granted expressly or tacitly. It takes the form of a rectangular sign visible from the public road, the content of which is set by the French Planning Code: identity of the beneficiary, date and number of the permit, nature of the project, area of the land, authorised floor area, height of the building, address of the town hall where the file can be consulted, and details of the means and time limits for challenging it. What is at stake is triggering the time limit for third-party challenges, which runs from the first day of a continuous two-month display period. Incomplete or interrupted display does not start that time limit running and leaves the project exposed to a late challenge: it is strongly advisable to have a commissaire de justice (judicial officer) draw up official reports at the beginning, during and at the end of the period.

What is the time limit for challenging a building permit?

Third parties have two months from the first day of a continuous two-month period of proper display of the sign on the site. Where the display was irregular or did not take place, this time limit does not run: a challenge remains possible for six months from completion of the works. Two points are decisive in practice. The challenge must be notified to the author of the decision and to its beneficiary within fifteen days of being lodged, failing which it will be inadmissible. And, for decisions taken on or after 28 November 2025, a request for reconsideration (recours gracieux) no longer extends the time limit for bringing court proceedings: you must therefore not wait for the town hall's response before applying to the administrative court.

What is the right of pre-emption?

The right of pre-emption is the power given to a local authority (or to a dedicated body) to acquire, as a priority and within certain previously defined areas, property being disposed of, with a view to carrying out operations in the public interest.

Is it compulsory to use an architect for a building permit?

Using an architect is the rule for any building permit application. The only notable exemption applies to individuals who build, or have built, for themselves a building whose floor area does not exceed 150 m², a threshold raised to 800 m² for agricultural buildings. A point often overlooked: this exemption does not apply to legal entities. A property holding company (SCI), including a family one, a property development company or a local authority must use an architect whatever the size of the project, failing which the application will be inadmissible.

Do you need a building permit for a conservatory (véranda)?

It depends on the area created and the location of the land. A conservatory is an extension: in an urban zone of a municipality covered by a PLU (local urban development plan), a prior declaration is sufficient up to 40 m² of floor area or footprint, and a building permit becomes mandatory above that. Everywhere else, the threshold is lowered to 20 m². Please note: in an urban zone, a building permit is again required from 20 m² where the extension brings the total floor area of the building above 150 m².

Do you need a building permit for a garage?

It depends on the size of the garage and its location. If it is attached to the existing building, it is an extension: prior declaration up to 40 m² in an urban zone of a municipality covered by a PLU, up to 20 m² elsewhere, and a building permit above that. If it is a detached garage, it is a new construction: no formalities up to 5 m², prior declaration from 5 to 20 m², building permit above 20 m². In an urban zone, a building permit is also required from 20 m² if the works bring the total floor area above 150 m².

Do you need a building permit to convert an attic?

Converting an attic is only subject to authorisation if it creates floor area or alters the external appearance of the building, for example by adding a roof window or a dormer. Where this is the case, a prior declaration is sufficient up to 40 m² of floor area created in an urban zone of a municipality covered by a PLU, and up to 20 m² elsewhere; above that, a building permit is required. In an urban zone, a building permit is also required from 20 m² if the works bring the total floor area of the building above 150 m².

How much does a building permit cost?

Filing the application is free: the town hall does not charge any processing fee. The real cost of a building permit lies in three items. First, planning taxes, chief among them the development tax (taxe d'aménagement), assessed on the taxable area using a flat-rate value per square metre revised each year, to which the rates voted by the municipality and the département apply; in Île-de-France, an office, retail or warehouse project is also subject to the charge for the creation of premises (redevance pour création de locaux). Second, design and project management fees, which vary according to the nature and complexity of the project. Finally, where applicable, the preventive archaeology levy. These items must be costed from the outset in the development appraisal: the development tax often represents an amount out of all proportion to the application costs.

What is the PLU?

The local urban development plan (Plan local d'urbanisme, PLU) sets the planning and building rules by dividing the territory into plots and zones with distinct legal regimes. For each plot, it shows the applicable planning rules as well as easements, access to utility networks and to the public road, and whether or not the plot can be built on.

Do you need a building permit for a swimming pool?

No, in most cases. A pool with a surface area of 10 m² or less is exempt from any formalities, except in a protected area. Between 10 m² and 100 m², a prior declaration is sufficient. A building permit is only required for a pool of more than 100 m². It is also required, whatever the surface area of the pool, where the pool is covered by a shelter more than 1.80 metres high. These thresholds do not exempt the project from complying with the PLU, which may lay down its own rules on siting, setbacks and footprint.

How can the designated use (destination) of a property be changed?

A change of designated use requires, at a minimum, a prior declaration. If the accompanying works alter the load-bearing structures or the façade of the building, a building permit is required. Two useful points. The French Planning Code distinguishes five uses and twenty sub-uses: moving from one sub-use to another within the same use is not, in itself, a change of use requiring authorisation, although the PLU may regulate it. In addition, certain changes of use are subject to a binding opinion, in particular that of the CDPENAF (commission for the preservation of natural, agricultural and forest areas) for a building located in an agricultural zone.

How can a pre-emption decision be challenged?

The owner and the ousted buyer may attempt to challenge the pre-emption decision. Before bringing litigation, it is possible to lodge a prior informal appeal (recours gracieux) with the holder of the pre-emption right within 2 months of notification of the decision. If the informal appeal is rejected by the holder, a contentious appeal must then be lodged with the administrative court within 2 months.

Grenoble, l'Isère et le massif de Belledonne
Explore all our resources
No items found.

A misdirected challenge means a lost season

In the mountains, the construction window is short and the litigation timetable will not wait for it. For projects linked to the 2030 Games, there is also a single court ruling without appeal. Let's check the time limit and the competent court together before any application is lodged.