NOVLAW AVOCATS (Laurent BIDAULT) assists public and semi-public bodies as project owner’s assistant (assistant à maîtrise d’ouvrage, AMO) in the preparation, drafting, award and performance of public procurement contracts (public contracts, concessions, calls for projects).
Article L. 2422-2 of the Code de la commande publique (French Public Procurement Code) provides that the project owner may award public contracts for project owner assistance covering one or more specialised matters, in particular specialist advice in a technical, financial, legal or administrative field.
The project owner, in other words the buyer, may therefore be assisted by a specialist legal adviser to carry out legal studies and analyses, notably to help it define its needs and identify the most appropriate contractual structure or the applicable rules on procedure, advertising and competitive tendering.
The AMO can assist the project owner in drafting the contract and in implementing it (award procedure, performance).
More generally, the AMO secures the contract and its award.
NOVLAW AVOCATS has recognised experience in project owner assistance.
On the legal side, the AMO carries out legal analyses and provides opinions, in particular on the contract or procedure to recommend; it drafts the contracts and ensures the legal soundness of the contract award procedures.
A legal AMO can step in at every phase of a project:
Ultimately, a legal AMO strengthens the legal reliability of your projects by carrying out analyses, building robust contractual frameworks and securing your procedures for awarding public contracts and concessions.
A public project is not decided solely at the moment the contract is signed. It is built upstream, during the structuring phase, and then unfolds over several years, from the tender process until the warranties expire, or even until the building is refurbished or demolished. At each of these stages, the decisions taken bind the project owner for the long term.
This support is organised around four phases: structuring the project (stages 1 to 3), award (stage 4), performance and warranties (stages 5 to 7) and, finally, the end of the building’s life (stage 8). Experience shows that the difficulties encountered during performance very often stem from the drafting of the contract documents several months or even several years earlier: this is precisely why the legal AMO should be involved from the structuring phase and kept on until the final settlement of the contract.
There are many advantages to using a legal AMO.
A legal AMO makes the project legally secure by identifying, and even resolving, potential difficulties upstream, thereby helping in particular to prevent disputes.
The AMO ensures that the contracts are balanced and protect the project owner’s interests.
Finally, using a legal AMO also saves the project owner time, as it relieves it of complex legal matters and allows it to focus on the more operational aspects of the project.
The project owner assistance provided by NOVLAW AVOCATS, and in particular by Laurent Bidault’s teams, covers every stage of the project life cycle:
The award phase attracts most of buyers’ attention, because it is governed by clearly identified rules on advertising, time limits and remedies. Yet performance is the longest and most costly phase, and the one that generates the most disputes: this is where delays, additional works, contractor defaults, damages claims and, ultimately, the real cost of the project are decided.
The legal AMO’s role during performance is not to replace the project manager (maître d’œuvre) or the buyer’s own departments. It deals with the decisions that legally bind the project owner: characterising a request from the contractor, choosing the right contractual instrument, complying with formal requirements on pain of irregularity, and building the file with a view to any future dispute.
The service order (ordre de service) is the instrument by which a works contract is directed. A late start order, a service order requiring services outside the scope of the contract or a service order issued without a contractual basis engages the project owner’s liability and entitles the contractor to compensation, or even to termination of the contract at the project owner’s fault. The CCAG Travaux (general administrative terms for works contracts) governs the form of these orders, their notification and the reservations the contractor may raise against them (see our complete guide to service orders).
Late-performance penalties, for their part, are never applied mechanically. They require an established triggering event, a statement drawn up after hearing both parties and a proper deduction in the statement of account. The administrative courts may set them aside where the delay is attributable to the buyer and reduce them where their amount is manifestly excessive in relation to the contract value. The AMO secures this point upstream, through the drafting of the clause, and downstream, by putting together the file for applying the penalties (see our guide to penalties in public contracts).
The contract may be modified during performance, but only in the cases exhaustively listed in the Code de la commande publique: review clauses provided for from the outset, additional services that have become necessary, unforeseen circumstances, change of contractor, non-substantial modifications and low-value modifications.
Two sets of ceilings must be handled with precision:
Where the contract was awarded under a formal procedure, some of these modifications also require a modification notice to be published in the Official Journal of the European Union. An incorrectly characterised amendment exposes the project owner to the annulment of the modification and to the payment being called into question, and exposes authorising officers and public accountants to personal liability. The AMO’s first task is therefore to characterise the request before drafting the amendment, not the other way round.
Under a lump-sum contract, the contractor is in principle entitled to payment for additional works only if they were ordered by the project owner or were essential to completing the works in accordance with good practice. In practice, such requests most often arrive at the end of the works, in the statement of claim (mémoire en réclamation), when evidence is hardest to gather.
The AMO sets up the audit trail: characterisation of the service, formalisation by service order or amendment, joint determination of new prices, and a decision to continue where the contract value is exceeded. Our analysis of additional works carried out without an amendment sets out the conditions under which such works may, or may not, be compensated.
Subcontracting is a recurring source of double payment for buyers. The subcontractor must be accepted and its payment terms approved by the project owner. Once the value of its services exceeds 600 euros including all taxes (Article R. 2193-10), it is paid directly by the buyer. Paying the main contractor instead exposes the public body to having to pay a second time.
Added to this are issues of chain subcontracting, the guarantees that may be required from the contractor and the interaction with assignments of receivables. Our resources on subcontracting in public contracts and on payment of a subcontractor entitled to direct payment cover these mechanisms.
Financial performance is governed by mandatory rules that the buyer applies at its own risk:
Abandonment of the site, mounting delays, judicial liquidation or repeated breaches of contractual obligations confront the project owner with a difficult choice: continue performance or bring it to an end. Both options carry a financial risk, and the second requires strict compliance with formalities.
The buyer may terminate an administrative contract in the event of a sufficiently serious fault by the other party or on public interest grounds, the latter entitling the contractor to compensation (Article L. 2195-3). The coercive measures provided for in the CCAGs (general administrative terms) – taking over the works directly, performance at the contractor’s cost and risk, replacement contract – require a prior formal notice, properly issued in both form and time limit, that has gone unheeded. An irregular formal notice is enough to undermine the entire procedure.
Our resources set out these mechanisms in detail: when a public contract can be terminated, the consequences of an irregular formal notice and performance at the contractor’s cost and risk and the replacement contract.
Acceptance (réception) is the act by which the project owner accepts the works, with or without reservations. Under the 2021 CCAG Travaux, the acceptance decision is notified to the contractor within thirty days of the report on the pre-acceptance inspections and takes effect on the date set for completion of the works (Article 41). It ends the contractual relationship as regards apparent defects and marks the starting point of the warranties.
Next comes the settlement of accounts, governed by Article 12 of the 2021 CCAG Travaux. The project owner notifies the final statement of account (décompte général), which the contractor returns signed, with or without reservations, within thirty days. If it is not notified in time, the contractor may send its own draft final statement of account, which becomes the final and definitive statement of account if the project owner does not respond within the ten-day period allowed: this is the mechanism of the tacit final statement of account, whose financial consequences are often underestimated.
The final and definitive statement of account makes the balance unalterable. In practice, a poorly managed statement of account costs far more than an award dispute. Our resources on the acceptance procedure for public works contracts and on the stages in drawing up the statement of account describe how it unfolds.
Acceptance opens the warranty period: the one-year warranty of completion (garantie de parfait achèvement), the two-year warranty of proper functioning for separable equipment, and the ten-year (decennial) warranty for damage that compromises the structural integrity of the works or renders them unfit for their intended purpose. Each warranty has its own conditions of enforcement, its own time limits and its own addressees.
The AMO identifies the appropriate legal basis for the defect observed, secures the notifications, arranges where necessary a court-appointed expert assessment or a preventive interim application (référé préventif), and ensures that the warranty of completion is properly coordinated with the statement of account, an issue that regularly gives rise to disputes.
Disputes arising during performance follow a procedure specific to public contracts. Under the 2021 CCAG Travaux, the contractor must submit a statement of claim whose content is prescribed; where the claim concerns the final statement of account, the statement of claim must be sent within thirty days of notification of the final statement of account and must restate, on pain of being time-barred, any earlier claims that remain unresolved (Article 55.1.1). Without a valid statement of claim, any subsequent court action is inadmissible.
For the project owner, these formalities are an opportunity: a carefully drafted response, reasoned item by item, settles a large share of claims without litigation. Where the dispute persists, it may be referred to an advisory committee for the amicable settlement of disputes or resolved through a settlement agreement, before any referral to the administrative courts.
Beyond one-off advice, project owner assistance during performance results in identifiable deliverables:
This support can be provided either under a dedicated AMO contract or as a one-off assignment on a contract already being performed.
Assisting a municipality with the drafting and award of a global energy performance contract
Assisting a département with the drafting and award of a public works contract
Assisting a municipality with the drafting and award of a public insurance contract
Assisting a public cultural institution with the drafting and award of an innovation partnership
Assisting a group of public bodies with the drafting and award of a public contract for IT services (software development and acquisition)
Assisting a public company with the drafting and award of a design-and-build contract
Assisting a public project owner in monitoring the performance of a works contract: amendments, additional works, penalties, statement of claim and preparation of the final statement of account
The time limit for lodging an appeal on points of law (pourvoi en cassation) against a judgment of an Administrative Court of Appeal is two months from notification of the court's decision. However, this time limit is reduced to 15 days where the case concerns summary proceedings (référé).
The term 'public buyer' covers the contracting authorities and contracting entities subject to the French Public Procurement Code. Examples include the State, local authorities and municipalities.
The innovation partnership differs from a conventional R&D contract in that it covers, within a single contract, both the research and development phase AND the acquisition of the solution developed, without any need to launch a new procedure for the purchase. By contrast, a pure R&D contract covers only the research phase, and the buyer must then organise a new procedure to acquire the solution. The innovation partnership is therefore better suited where the buyer has a clearly identified need but no existing solution.
The time limit for appealing a decision of an administrative court (tribunal administratif) is two months from notification of the judgment. This time limit is only 15 days if the decision is an interim relief order (référé).
The French Public Procurement Code (Code de la commande publique) imposes three so-called formalised procedures where the value of the public contract exceeds the procedural thresholds: the call for tenders (open or restricted), the negotiated procedure, or the competitive dialogue.
A public contract is a contract for pecuniary interest concluded by a public buyer with an economic operator to meet its needs for works, supplies or services. Depending on its value or subject matter, the public contract must be awarded following an advertising and competitive tendering procedure.
A global contract (marché global) is a public contract with a composite subject matter, whereby a buyer entrusts an economic operator with an overall assignment comprising services of different kinds (design/construction/operation/maintenance) in return for payment of a price.
Where the estimated value of a contract is below the thresholds for formalised procedures, the buyer may use an adapted procedure contract (marché à procédure adaptée, MAPA). The terms of the advertising and competitive tendering procedure are freely determined by the buyer.
Acceptance of works under a public contract is the act by which the project owner accepts the works carried out, with or without reservations. It marks the starting point of the statutory guarantees (completion, two-year and ten-year) and transfers custody of the works to the project owner. Acceptance may be granted subject to reservations, which must be lifted within an agreed period, or refused if the works have significant defects.
Yes, up to €140,000 excluding VAT since 1 July 2026, provided that the innovative nature of the solution acquired can be demonstrated. This threshold derives from Article 16 of Law No. 2026-403 of 26 May 2026 on the simplification of economic life, which does not set any amount but refers to the European threshold applicable to supply and service contracts awarded by central government authorities: it will therefore change with each biennial revision, and Article R. 2122-9-1 of the French Public Procurement Code still refers to the former amount of €100,000 excluding VAT. The innovative nature must be documented before the contract is awarded, as it is the condition for using the mechanism and the first point of vulnerability in the event of a challenge. Above this threshold, the innovation partnership under Article L. 2172-3 or the negotiated procedure under Article R. 2124-3 of the same Code offer suitable routes.
Incorporating BIM into a public works contract involves drafting specific contractual documents: a BIM agreement defining the rules of collaboration, a BIM protocol specifying the expected levels of development (LOD), and specific clauses in the CCAP (special administrative terms and conditions) governing the uses of the model, liability in the event of errors and the arrangements for delivering data at the end of the works.
An unsuccessful bidder may apply to the administrative court for “pre-contractual interim relief” (référé précontractuel), before the contract is signed by the buyer, to have a breach of the advertising and competitive tendering obligations sanctioned. Once the contract has been signed, other remedies exist (contractual interim relief or référé contractuel, and actions challenging the validity of the contract). Your lawyer's responsiveness is decisive here (very short time limits of 11 or 16 days).
The estimated value of a public contract is based on the total amount payable, excluding VAT, as estimated by the contracting authority. The value is calculated over the entire term of the contract, including renewals and options. It is this estimated value that determines the applicable procedural thresholds and the advertising and competitive tendering obligations.
Yes, through routes that differ depending on the nature of the scheme. Where the procedure falls within public procurement, pre-contractual interim relief (référé précontractuel) is available before the contract is signed. In other cases, the rejection is an administrative decision that may be challenged by an action for annulment (recours pour excès de pouvoir), the court's review then focusing in particular on compliance with the rules of the call for projects, equal treatment of candidates and the absence of any manifest error of assessment.
In public construction, the public project owner may be held liable for failing to meet its obligations: inadequate preliminary studies, poor definition of needs, or failings in the management and supervision of the works. Liability may also arise towards third parties (local residents, users) for damage caused by the public works. These disputes fall within the jurisdiction of the administrative court.
Yes, the innovative procurement scheme was specifically designed to make it easier for SMEs and start-ups to access public procurement. The exemption threshold, raised to €140,000 excluding VAT since 1 July 2026 by Law No. 2026-403 of 26 May 2026 on simplifying economic life, allows public buyers to deal directly with a young company without organising a lengthy and costly procedure. Buyers can also use sourcing and calls for projects to identify innovative SMEs before launching their procedure.
A framework agreement is a contract whose purpose is to establish the rules governing the purchase orders to be issued or the terms governing the subsequent contracts to be awarded during a given period, in particular with regard to prices and, where applicable, the quantities envisaged. It is subject to the same award rules as public contracts.
No. The standstill period runs from the date on which the buyer sends the rejection notification, not from its receipt by the unsuccessful candidate. Postal delivery time therefore eats into your window for action, which argues for reacting immediately upon receipt of the rejection letter.
No. The standstill period is calculated in calendar days, from date to date, without being carried over to the next working day. If it ends on a Saturday, Sunday or public holiday, the buyer may sign the contract from the next working day: the application for pre-contractual interim relief must therefore be filed before that deadline.

Every situation deserves a clear and pragmatic analysis. Novlaw helps you secure your decisions, anticipate risks and defend your interests.