Secure your public contracts for sports facilities

Contents
Our specialists
Maïté Cano
Laurent Bidault

In brief: public contracts and delegations relating to sports facilities (swimming pools, sports halls, stadiums, ice rinks, outdoor facilities) cover construction, renovation and operation. Three choices drive the risk: the contractual structure (works contract, global performance contract or public service delegation, DSP), the allocation of operating and safety risks, and the attendance targets set in the contract. Novlaw Avocats advises local authorities acting as project owners as well as contractors, operators and concession holders.

In sports-related public contracts, the risk is not limited to building a facility or signing an operating agreement. It often arises from the allocation of responsibilities between the local authority and the operator for user safety, from the attendance or performance targets set in the contract, and from the legal structure chosen: works contract, global performance contract or public service delegation.

In other words, in this sector the challenge is not only to launch or win the tender. It is to avoid finding yourself, a few months after the facility opens, exposed on safety, maintenance or continuity obligations that were not adequately addressed in the contract.

Novlaw Avocats advises local authorities, construction companies, sports facility operators, public service concession holders and federations involved in public contracts and delegations relating to swimming pools, sports halls, stadiums, ice rinks and outdoor sports facilities.

For the local authority: choosing the right structure and keeping control of the facility

For a local authority, a sports facility is both a major investment and a public service whose quality and safety engage its liability.

  • Choosing the appropriate structure (works contract followed by an operating contract, global performance contract, design-and-build or DSP) by assessing the operating risk actually transferred to the operator;
  • Defining a realistic programme, attendance targets and business plan, to avoid a contentious renegotiation during the contract;
  • Monitoring performance: the operator’s accounts, the concession holder’s annual reports, oversight of the maintenance and renewal of the facilities;
  • Setting proportionate unavailability and quality penalties, with clearly defined grounds for exemption (administrative closure, bad weather, external events);
  • Securing acceptance of the works, the authorisations to open to the public and the warranty of completion (garantie de parfait achèvement);
  • Providing for the handover of assets and the end of the contract so as to preserve the option of retendering or bringing the facility back in-house;
  • Giving reasons for the award decision and observing the standstill period to secure signature.

Further reading: local authorities law, public services law and project owner assistance (AMO) in public procurement.

Securing the award phase: public contract, DSP or global performance contract

The choice of contractual structure shapes the entire life of the project. A new sports facility may be built and operated under a design-and-build contract or a global performance contract, or entrusted to a third party under a public service delegation (DSP).

  • Analysis of the tender documents and identification of unbalanced clauses, particularly on the allocation of operating risks between the local authority and the operator;
  • Assistance in structuring consortia for projects combining construction and operation;
  • Securing bids or specifications in a DSP procedure, particularly the forecast business and financial plan;
  • Checking consistency between attendance targets, the fee and the risk-sharing clauses.

Further reading: The global performance contract and the design-and-build contract.

From construction to opening: managing performance

Where the contract covers the construction or renovation of a sports facility, the usual difficulties of works contracts are compounded by sector-specific constraints: federation approval, technical standards for competitions, certification by safety committees.

  • Securing service orders and requests for additional works during construction;
  • Support during acceptance procedures, with particular attention to federation standards and the operating authorisations required to host the public and competitions;
  • Handling third-party challenges (local residents, associations) liable to delay the delivery of a major sports facility (stadium, aquatic centre).

Further reading: Building permits and public works contracts.

Safety of facilities and users: the heart of the risk

In operating a sports facility, user safety is both a regulatory requirement and the main source of litigation risk and of liability claims against the operator and the owning local authority alike.

  • Analysis of the regulatory obligations specific to sports establishments open to the public (ERP): classification, safety committees, federation standards;
  • Framing supervision obligations and staff qualification requirements (qualified lifeguards, certified sports instructors);
  • Defending the operator or the local authority in the event of an accident or a claim against them, in liaison with insurers;
  • Securing preventive maintenance clauses and the upkeep of technical installations (pools, water treatment systems, structures).

Financial disputes: fees, penalties and economic balance

The end of a sports project, particularly under a DSP, is often when disagreements over the economic balance of the contract come to a head.

  • For the concession holder: challenging penalties imposed for unavailability of the facility or failure to meet attendance targets that disregard external causes (administrative closure, bad weather, health crisis);
  • For the local authority: reasoned application of penalties, auditing of accounts and recovery of the fee;
  • Renegotiating or challenging the public property occupation fee where operating conditions change substantially;
  • Drafting the statement of claim (mémoire en réclamation) in the event of disagreement over the works account or unpaid operating services;
  • Support for the local authority or the concession holder in the event of termination or forfeiture (déchéance) of a DSP.

Further reading: Dispute resolution in public contracts and our guide to penalties.

Legal management of subcontracting and specialist service providers

Operating a sports facility often involves specialist providers (technical maintenance, sports coaching, on-site catering). We secure subcontracting declarations and handle disputes arising from a provider’s default.

Further reading: FAQ: subcontracting and public contracts.

Favouring amicable dispute resolution

Litigation before the administrative courts is not always the most appropriate solution, particularly where the facility must remain open to the public and user clubs. Wherever relevant, we favour structured negotiation and mediation.

Further reading: Using mediation.

Challenging the award procedure, or securing it

A bidder unsuccessful in the award of a sports-related public contract or public service delegation may apply to the administrative court before the contract is signed. The local authority must be able to defend its choice and observe the standstill period.

Further reading: Pre-contractual interim relief (référé précontractuel) lawyer.

Frequently asked questions about sports-related public contracts

Should a sports facility be operated under a DSP or a public contract?

It all depends on the operating risk. If the operator bears a real risk linked to operating the service, in particular the attendance and revenue risk, the contract falls under the regime governing concessions and public service delegations. Otherwise, it is a public contract paid for by the local authority.

Who is responsible for the safety of users of a delegated swimming pool or sports hall?

Liability depends on the contract and the facts at issue. The operator generally takes on supervision and routine maintenance, but the owning local authority may be held liable, notably for design defects or major maintenance. That is why the allocation must be set out precisely in the contract.

Can a concession holder challenge penalties for unavailability of the facility?

Yes, where the unavailability results from an external cause (administrative closure, bad weather, health crisis) or from a decision of the local authority. The local authority, for its part, must apply penalties on the basis of jointly established findings and under the conditions laid down in the contract.

How can a local authority take back a sports facility at the end of the contract?

By providing from the outset for what happens to the assets, staff and data, and then organising the transition with the outgoing concession holder. Bringing a facility back in-house or retendering it must be prepared several months before the contract expires.

Typical Novlaw Avocats assignments in the sports sector

  • Choosing the contractual structure (DSP or global performance contract) for the construction and operation of a sports facility, for a local authority or for a bidder;
  • Drafting or reviewing the contract, the business plan and the penalty and asset handover clauses;
  • Assisting a local authority or a business in pre-contractual interim relief proceedings concerning the award of a delegation to manage sports facilities;
  • Applying or challenging unavailability penalties;
  • Defending an operator or a local authority facing a liability claim following an accident.

Why choose Novlaw Avocats for your sports-related public contracts?

  • 360° expertise: we combine our command of public procurement law with expertise in construction law and sports law;
  • Insight from both sides of the contract: local authorities acting as project owners, contractors, operators and concession holders;
  • Responsiveness under tight deadlines: reservations, claims and interim applications must be made quickly to preserve your rights;
  • End-to-end support: from the choice of contractual structure to construction, then operation and disputes;
  • A local presence: Paris, Lyon and Lille.

Explore our complementary expertise: public procurement lawyer and sports law.

Ils ont fait appel à NOVLAW avocats

Chargement…

Frequently asked questions on

Public procurement

What is the time limit for lodging an appeal on points of law against a judgment of an Administrative Court of Appeal?

The time limit for lodging an appeal on points of law (pourvoi en cassation) against a judgment of an Administrative Court of Appeal is two months from notification of the court's decision. However, this time limit is reduced to 15 days where the case concerns summary proceedings (référé).

Who is the public buyer?

The term 'public buyer' covers the contracting authorities and contracting entities subject to the French Public Procurement Code. Examples include the State, local authorities and municipalities.

What are the differences between an innovation partnership and an R&D contract?

The innovation partnership differs from a conventional R&D contract in that it covers, within a single contract, both the research and development phase AND the acquisition of the solution developed, without any need to launch a new procedure for the purchase. By contrast, a pure R&D contract covers only the research phase, and the buyer must then organise a new procedure to acquire the solution. The innovation partnership is therefore better suited where the buyer has a clearly identified need but no existing solution.

What is the time limit for appealing a decision of an administrative court?

The time limit for appealing a decision of an administrative court (tribunal administratif) is two months from notification of the judgment. This time limit is only 15 days if the decision is an interim relief order (référé).

What is a formalised procedure?

The French Public Procurement Code (Code de la commande publique) imposes three so-called formalised procedures where the value of the public contract exceeds the procedural thresholds: the call for tenders (open or restricted), the negotiated procedure, or the competitive dialogue.

What is a public contract?

A public contract is a contract for pecuniary interest concluded by a public buyer with an economic operator to meet its needs for works, supplies or services. Depending on its value or subject matter, the public contract must be awarded following an advertising and competitive tendering procedure.

What is a global contract (marché global)?

A global contract (marché global) is a public contract with a composite subject matter, whereby a buyer entrusts an economic operator with an overall assignment comprising services of different kinds (design/construction/operation/maintenance) in return for payment of a price.

What is a MAPA?

Where the estimated value of a contract is below the thresholds for formalised procedures, the buyer may use an adapted procedure contract (marché à procédure adaptée, MAPA). The terms of the advertising and competitive tendering procedure are freely determined by the buyer.

How does acceptance of works take place under a public contract?

Acceptance of works under a public contract is the act by which the project owner accepts the works carried out, with or without reservations. It marks the starting point of the statutory guarantees (completion, two-year and ten-year) and transfers custody of the works to the project owner. Acceptance may be granted subject to reservations, which must be lifted within an agreed period, or refused if the works have significant defects.

Can a local authority acquire an innovative solution without competitive tendering?

Yes, up to €140,000 excluding VAT since 1 July 2026, provided that the innovative nature of the solution acquired can be demonstrated. This threshold derives from Article 16 of Law No. 2026-403 of 26 May 2026 on the simplification of economic life, which does not set any amount but refers to the European threshold applicable to supply and service contracts awarded by central government authorities: it will therefore change with each biennial revision, and Article R. 2122-9-1 of the French Public Procurement Code still refers to the former amount of €100,000 excluding VAT. The innovative nature must be documented before the contract is awarded, as it is the condition for using the mechanism and the first point of vulnerability in the event of a challenge. Above this threshold, the innovation partnership under Article L. 2172-3 or the negotiated procedure under Article R. 2124-3 of the same Code offer suitable routes.

How can BIM be incorporated into a public works contract?

Incorporating BIM into a public works contract involves drafting specific contractual documents: a BIM agreement defining the rules of collaboration, a BIM protocol specifying the expected levels of development (LOD), and specific clauses in the CCAP (special administrative terms and conditions) governing the uses of the model, liability in the event of errors and the arrangements for delivering data at the end of the works.

How can the award of a public contract be challenged?

An unsuccessful bidder may apply to the administrative court for “pre-contractual interim relief” (référé précontractuel), before the contract is signed by the buyer, to have a breach of the advertising and competitive tendering obligations sanctioned. Once the contract has been signed, other remedies exist (contractual interim relief or référé contractuel, and actions challenging the validity of the contract). Your lawyer's responsiveness is decisive here (very short time limits of 11 or 16 days).

How is the value of a public contract calculated?

The estimated value of a public contract is based on the total amount payable, excluding VAT, as estimated by the contracting authority. The value is calculated over the entire term of the contract, including renewals and options. It is this estimated value that determines the applicable procedural thresholds and the advertising and competitive tendering obligations.

Can a candidate rejected from a call for projects challenge the decision?

Yes, through routes that differ depending on the nature of the scheme. Where the procedure falls within public procurement, pre-contractual interim relief (référé précontractuel) is available before the contract is signed. In other cases, the rejection is an administrative decision that may be challenged by an action for annulment (recours pour excès de pouvoir), the court's review then focusing in particular on compliance with the rules of the call for projects, equal treatment of candidates and the absence of any manifest error of assessment.

What is the liability of the public project owner in the event of a construction defect?

In public construction, the public project owner may be held liable for failing to meet its obligations: inadequate preliminary studies, poor definition of needs, or failings in the management and supervision of the works. Liability may also arise towards third parties (local residents, users) for damage caused by the public works. These disputes fall within the jurisdiction of the administrative court.

Can an SME bid for an innovative public procurement contract?

Yes, the innovative procurement scheme was specifically designed to make it easier for SMEs and start-ups to access public procurement. The exemption threshold, raised to €140,000 excluding VAT since 1 July 2026 by Law No. 2026-403 of 26 May 2026 on simplifying economic life, allows public buyers to deal directly with a young company without organising a lengthy and costly procedure. Buyers can also use sourcing and calls for projects to identify innovative SMEs before launching their procedure.

What is a framework agreement?

A framework agreement is a contract whose purpose is to establish the rules governing the purchase orders to be issued or the terms governing the subsequent contracts to be awarded during a given period, in particular with regard to prices and, where applicable, the quantities envisaged. It is subject to the same award rules as public contracts.

Does the standstill period run from receipt of the rejection letter?

No. The standstill period runs from the date on which the buyer sends the rejection notification, not from its receipt by the unsuccessful candidate. Postal delivery time therefore eats into your window for action, which argues for reacting immediately upon receipt of the rejection letter.

Is the standstill period extended if it ends on a Saturday or a public holiday?

No. The standstill period is calculated in calendar days, from date to date, without being carried over to the next working day. If it ends on a Saturday, Sunday or public holiday, the buyer may sign the contract from the next working day: the application for pre-contractual interim relief must therefore be filed before that deadline.

Explore all our resources
No items found.

Let’s talk about your project or your situation

Every situation deserves a clear and pragmatic analysis. Novlaw helps you secure your decisions, anticipate risks and defend your interests.