Secure the award and performance of your contracts

Contents
Our specialists
Laurent Bidault

In brief: a public works contract is won or lost as much at the award stage as during performance: service orders, additional works, penalties, acceptance, the final account and post-completion warranties. Novlaw Avocats advises public project owners as well as construction contractors and project managers (maîtres d'œuvre).

In the construction, building and civil engineering sector, signing the contract is only the beginning of the story.

Between unforeseen site conditions, soaring raw material prices, disputable service orders and the complexity of acceptance or of the procedure for drawing up the final account, the viability of a project often depends on the legal management of its performance.

Novlaw Avocats, specialists in public procurement law, advise public project owners (local authorities, public bodies, social housing landlords), works and construction contractors (civil engineering, structural works, finishing works, etc.) and project managers throughout France.

For public project owners: preparing, managing and securing your works contract

A public project owner keeps control of its costs and deadlines when its contract is sound from the tender stage and managed methodically throughout the works.

  • Define the programme and the requirement, carry out preliminary surveys (ground, utility networks, diagnostics) to limit unforeseen difficulties, and divide the contract into coherent lots;
  • Draft a CCAP (special administrative terms) and a CCTP (special technical terms) consistent with the CCAG Travaux (general administrative terms for works) and free of contradictions, which are the primary source of disputes;
  • Set award criteria linked to the subject matter of the contract and score bids in a traceable manner, in order to secure the award: see neutralisation of scoring criteria and the standstill period;
  • Examine abnormally low tenders before awarding: see abnormally low tenders;
  • Formalise service orders and request additional works only by way of an amendment, within the limits set by the Code de la commande publique (Public Procurement Code) for the modification of contracts;
  • Apply late-completion penalties methodically: contractual schedule, site meeting minutes, formal notice where appropriate and a statement of reasons, so that they withstand any challenge: see our guide to penalties;
  • Organise acceptance with precise reservations, followed by the one-year completion warranty: see the completion warranty (garantie de parfait achèvement) and custody of the site before acceptance;
  • Manage the drawing up of the final account within the time limits of the CCAG Travaux and take action against the builders within the time limits in the event of defects;
  • Where a contractor defaults, terminate for breach methodically and ensure continuity of the works: see termination for repeated breaches.

Further reading: local authorities law, project owner assistance (AMO) in public procurement, public project management contracts and construction law.

Securing the award stage and your response to calls for tender

Anticipation is the key to a profitable public contract. We assist contractors from the moment the call for tender is published to avoid pitfalls upstream, and project owners to make their tender documents robust before publication:

  • Review of the tender documents (DCE): we identify unbalanced clauses in the CCAP and legal risks before you submit your bid.
  • Contractual structuring: we assist you in forming consortia (joint or joint and several co-contracting) and in drafting consortium agreements that clearly define each member's responsibilities.

From the commencement Service Order (OS) to Acceptance: keeping control of the works  

The performance of a public works contract can prove to be a minefield, given the formalities and strict framework imposed by the contract documents. A simple oversight in the time limit for responding to a service order can be costly.

Managing unforeseen events and additional works

This is undoubtedly the most frequent source of disputes: the public buyer or the project manager requests changes during the works without necessarily formalising the request, in particular through an amendment.

  • Securing service orders: we help you express your reservations on Service Orders (OS) within the prescribed time limits (15 days under the CCAG Travaux) in order to preserve your rights to compensation.
  • New works, works essential to completing the structure in accordance with good practice, works required because of another contractor's default: we characterise the requests and situations legally in order to secure regularisation by amendment and payment for these works or, on the project owner's side, to assess whether they are justified and to control the expenditure.

Unforeseen difficulties (sujétions imprévues)

Discovery of polluted soil, unrecorded utility networks... We provide legal support to have this situation recognised and to obtain compensation for unforeseen technical difficulties or, where you are the project owner, to assess whether the conditions are met.

__wf_reserved_inherit

Legal management of subcontracting

On a construction site, the subcontracting chain is governed by strict rules (Code de la commande publique, Law of 1975). Poor management can block payments or expose you to liability. We act to:

  • Secure subcontracting declarations and the public buyer's approval of payment terms.
  • Assist you with direct payment procedures.
  • Handle disputes relating to a subcontractor's default or to allegations of undeclared subcontracting.

Further reading: FAQ: subcontracting and public contracts

Beyond acceptance: post-completion warranties

Our support does not end with the signature of the final account (DGD). The years following handover of the works are often when defects appear. We defend you, or bring claims against the parties liable, under the statutory warranties:

  • The one-year completion warranty (Garantie de Parfait Achèvement, GPA): handling reservations at acceptance and defects reported in the following year.
  • The two-year warranty (proper functioning): for equipment that can be separated from the structure.
  • The ten-year warranty (garantie décennale): for damage that compromises the soundness of the structure or renders it unfit for its intended purpose.

Financial disputes: final account, penalties and claims

The end of the works is often when tensions come to a head. Our role is to "clean up" the file and sort through the claims in order to determine the sums due.

Challenging or applying late-completion penalties

Public buyers generally apply late-completion penalties automatically, without necessarily taking into account legitimate causes that may explain the delay (additional works, bad weather, delays by other trades, waiting for approval of drawings).

In this context, we work alongside you to analyse the works schedule and site meeting minutes in order to demonstrate that the delay is not attributable to you, and/or to ask the administrative court to reduce the penalties if they are manifestly excessive. On the project owner's side, we secure the application of penalties so that they are properly reasoned and withstand challenge.

Drawing up the final and definitive account (DGD)

The DGD (Décompte Général et Définitif) is in a way the financial "arbiter" of the contract. Once signed by the parties, it is final and therefore binding and incontestable. If you disagree with it, you must therefore take care not to sign it and, above all, challenge it within the time limits set out in the contract documents (namely the CCAP and the applicable CCAG).

  • The statement of claim (Mémoire en Réclamation): this is the key document. If you sign the final account without expressing any reservation, or if you do not serve your statement of claim within the time limit (under the CCAG Travaux, 30 days from notification of the account), you lose any possibility of challenging it and therefore, potentially, of claiming, for example, that certain works have not been paid for.

Further reading: Dispute resolution in public contracts

In this context, we assist you in drafting the statement of claim, which must be reasoned in fact and in law, well argued and quantified, or in analysing the claim received where you are the project owner.

Further reading: Our template statement of claim.

  • The tacit final and definitive account (DGD): we assist you throughout the procedure for drawing up the account, in particular in managing procedural time limits, claims for compensation for additional works or delays, and penalties.

Further reading: The stages of the procedure for drawing up the account in a public works contract

Favouring amicable settlement (ADR) and the CCRA

Litigation before the administrative courts can sometimes prove lengthy and costly. To preserve your cash flow and your relationships with your contractual partners, we favour Alternative Dispute Resolution (ADR, MARD) whenever possible. We prepare and argue cases before the Advisory Committees for Amicable Settlement of disputes (CCRA) or in mediation proceedings, in order to reach a satisfactory settlement agreement on financial claims.

Construction and planning go hand in hand

A public works contract is carried out on a plot of land, in a town, subject to strict planning rules. Blockages on a public construction site sometimes stem from a challenge to the building permit or a land issue. Thanks to our cross-disciplinary expertise, we handle the matter from every angle:

  • Building permit issues: if the contract is blocked by a challenge from local residents, our planning law team steps in to defend the authorisation.
  • Pre-emption and land: we secure public property aspects ahead of the works.

Challenging the award, or securing it

An unsuccessful bidder may bring proceedings before the contract is signed, and the project owner must be able to defend its choice. See our pre-contractual interim relief (référé précontractuel) lawyers and the notion of harmed interest.

Frequently asked questions on public works contracts

How can a public project owner limit additional works?

By preparing reliable preliminary surveys, drafting a consistent CCAP and CCTP, formalising every service order and ordering new works only by way of an amendment, within the limits set by the Code de la commande publique for the modification of contracts.

Can a late-completion penalty be applied automatically?

It applies in accordance with the terms of the contract and the CCAG, but it can still be challenged where the delay has legitimate causes (additional works, bad weather, delays by other trades, late approval of drawings). The court may reduce a manifestly excessive penalty.

What happens if a contractor does not challenge the final account within the time limit?

In principle, it loses any possibility of challenging it. Under the CCAG Travaux, the statement of claim must be served within 30 days of notification of the account.

What can a public project owner do when a contractor defaults?

It must record the breach, serve formal notice on the contractor under the conditions of the contract and then, if necessary, terminate the contract for breach and ensure continuity of the works, in particular through a replacement contract. Each step must be documented.

Typical Novlaw Avocats engagements in public works contracts

  • Audit of the DCE, CCAP and CCTP, for a project owner before publication or for a contractor before submitting its bid;
  • Assisting an economic operator or a project owner in pre-contractual interim relief proceedings concerning the award of a public construction contract;
  • Project owner assistance for the preparation, award and performance of a design-and-build contract for the refurbishment and upgrading of an office building;
  • Project owner assistance for the preparation, award and performance of a global energy performance contract for the construction of a school;
  • Assisting an economic operator following the rejection of its statement of claim, or a project owner in analysing a claim.

Why choose Novlaw Avocats for your works contracts?

Choosing Novlaw Avocats means opting for a legal partner who understands the realities on the ground and the financial imperatives of works and construction projects, on the project owner's side as well as the contractor's.

  • All-round expertise: a public contract always sits within a complex environment, so we combine our command of public contract law with in-depth expertise in construction law and planning law.
  • Responsiveness to tight deadlines: public procurement law is a minefield of formalities and time limits. Whether it is a matter of expressing reservations on a Service Order or challenging a final account (DGD) within 30 days so as not to lose your rights, we act quickly to secure your position.
  • End-to-end support: we advise all parties involved in construction (civil engineering contractors, project managers, project owners) throughout France. We are at your side from the award of the contract through to the resolution of disputes.
  • A pragmatic, results-driven approach: our role is not only to practise law, but to audit your files, characterise your claims legally and secure the financial balance of the project, whether that means fair payment for the works or control of public expenditure.

Frequently asked questions on

Public procurement

What is the time limit for lodging an appeal on points of law against a judgment of an Administrative Court of Appeal?

The time limit for lodging an appeal on points of law (pourvoi en cassation) against a judgment of an Administrative Court of Appeal is two months from notification of the court's decision. However, this time limit is reduced to 15 days where the case concerns summary proceedings (référé).

Who is the public buyer?

The term 'public buyer' covers the contracting authorities and contracting entities subject to the French Public Procurement Code. Examples include the State, local authorities and municipalities.

What are the differences between an innovation partnership and an R&D contract?

The innovation partnership differs from a conventional R&D contract in that it covers, within a single contract, both the research and development phase AND the acquisition of the solution developed, without any need to launch a new procedure for the purchase. By contrast, a pure R&D contract covers only the research phase, and the buyer must then organise a new procedure to acquire the solution. The innovation partnership is therefore better suited where the buyer has a clearly identified need but no existing solution.

What is the time limit for appealing a decision of an administrative court?

The time limit for appealing a decision of an administrative court (tribunal administratif) is two months from notification of the judgment. This time limit is only 15 days if the decision is an interim relief order (référé).

What is a formalised procedure?

The French Public Procurement Code (Code de la commande publique) imposes three so-called formalised procedures where the value of the public contract exceeds the procedural thresholds: the call for tenders (open or restricted), the negotiated procedure, or the competitive dialogue.

What is a public contract?

A public contract is a contract for pecuniary interest concluded by a public buyer with an economic operator to meet its needs for works, supplies or services. Depending on its value or subject matter, the public contract must be awarded following an advertising and competitive tendering procedure.

What is a global contract (marché global)?

A global contract (marché global) is a public contract with a composite subject matter, whereby a buyer entrusts an economic operator with an overall assignment comprising services of different kinds (design/construction/operation/maintenance) in return for payment of a price.

What is a MAPA?

Where the estimated value of a contract is below the thresholds for formalised procedures, the buyer may use an adapted procedure contract (marché à procédure adaptée, MAPA). The terms of the advertising and competitive tendering procedure are freely determined by the buyer.

How does acceptance of works take place under a public contract?

Acceptance of works under a public contract is the act by which the project owner accepts the works carried out, with or without reservations. It marks the starting point of the statutory guarantees (completion, two-year and ten-year) and transfers custody of the works to the project owner. Acceptance may be granted subject to reservations, which must be lifted within an agreed period, or refused if the works have significant defects.

Can a local authority acquire an innovative solution without competitive tendering?

Yes, up to €140,000 excluding VAT since 1 July 2026, provided that the innovative nature of the solution acquired can be demonstrated. This threshold derives from Article 16 of Law No. 2026-403 of 26 May 2026 on the simplification of economic life, which does not set any amount but refers to the European threshold applicable to supply and service contracts awarded by central government authorities: it will therefore change with each biennial revision, and Article R. 2122-9-1 of the French Public Procurement Code still refers to the former amount of €100,000 excluding VAT. The innovative nature must be documented before the contract is awarded, as it is the condition for using the mechanism and the first point of vulnerability in the event of a challenge. Above this threshold, the innovation partnership under Article L. 2172-3 or the negotiated procedure under Article R. 2124-3 of the same Code offer suitable routes.

How can BIM be incorporated into a public works contract?

Incorporating BIM into a public works contract involves drafting specific contractual documents: a BIM agreement defining the rules of collaboration, a BIM protocol specifying the expected levels of development (LOD), and specific clauses in the CCAP (special administrative terms and conditions) governing the uses of the model, liability in the event of errors and the arrangements for delivering data at the end of the works.

How can the award of a public contract be challenged?

An unsuccessful bidder may apply to the administrative court for “pre-contractual interim relief” (référé précontractuel), before the contract is signed by the buyer, to have a breach of the advertising and competitive tendering obligations sanctioned. Once the contract has been signed, other remedies exist (contractual interim relief or référé contractuel, and actions challenging the validity of the contract). Your lawyer's responsiveness is decisive here (very short time limits of 11 or 16 days).

How is the value of a public contract calculated?

The estimated value of a public contract is based on the total amount payable, excluding VAT, as estimated by the contracting authority. The value is calculated over the entire term of the contract, including renewals and options. It is this estimated value that determines the applicable procedural thresholds and the advertising and competitive tendering obligations.

Can a candidate rejected from a call for projects challenge the decision?

Yes, through routes that differ depending on the nature of the scheme. Where the procedure falls within public procurement, pre-contractual interim relief (référé précontractuel) is available before the contract is signed. In other cases, the rejection is an administrative decision that may be challenged by an action for annulment (recours pour excès de pouvoir), the court's review then focusing in particular on compliance with the rules of the call for projects, equal treatment of candidates and the absence of any manifest error of assessment.

What is the liability of the public project owner in the event of a construction defect?

In public construction, the public project owner may be held liable for failing to meet its obligations: inadequate preliminary studies, poor definition of needs, or failings in the management and supervision of the works. Liability may also arise towards third parties (local residents, users) for damage caused by the public works. These disputes fall within the jurisdiction of the administrative court.

Can an SME bid for an innovative public procurement contract?

Yes, the innovative procurement scheme was specifically designed to make it easier for SMEs and start-ups to access public procurement. The exemption threshold, raised to €140,000 excluding VAT since 1 July 2026 by Law No. 2026-403 of 26 May 2026 on simplifying economic life, allows public buyers to deal directly with a young company without organising a lengthy and costly procedure. Buyers can also use sourcing and calls for projects to identify innovative SMEs before launching their procedure.

What is a framework agreement?

A framework agreement is a contract whose purpose is to establish the rules governing the purchase orders to be issued or the terms governing the subsequent contracts to be awarded during a given period, in particular with regard to prices and, where applicable, the quantities envisaged. It is subject to the same award rules as public contracts.

Does the standstill period run from receipt of the rejection letter?

No. The standstill period runs from the date on which the buyer sends the rejection notification, not from its receipt by the unsuccessful candidate. Postal delivery time therefore eats into your window for action, which argues for reacting immediately upon receipt of the rejection letter.

Is the standstill period extended if it ends on a Saturday or a public holiday?

No. The standstill period is calculated in calendar days, from date to date, without being carried over to the next working day. If it ends on a Saturday, Sunday or public holiday, the buyer may sign the contract from the next working day: the application for pre-contractual interim relief must therefore be filed before that deadline.

Explore all our resources
No items found.

Let's talk about your project or your situation

Every situation deserves a clear and pragmatic analysis. Novlaw helps you secure your decisions, anticipate risks and defend your interests.